Most commercial builders run a job across four systems and a shared drive
The estimate in one, the cost report in a spreadsheet, the RFIs in email, the claims in Word. SmarteBuild Commercial keeps the job in one place, so a variation priced on Monday is in Thursday's forecast and next month's claim without anyone retyping it.
Win
Take-off, bill of quantities, tenders out and quotes compared
Buy
Scope of works, orders, prequalified and insured subcontractors
Contract
Subcontracts, head contract schedule of values, approvals
Build
Drawings, RFIs, submittals, ITPs, safety, diary, by location
Claim
Client claims, subcontractor claims, retention, month-end
Hand over
Defects by unit, signed handover, retention released
Priced once, committed once, spent once. The forecast reads all three.
Every arrow is a link, not a re-key. Approvals sit on each one: nothing becomes committed or spent until the right person has signed it off.
Know the forecast final cost before the month closes, not after
Budget, approved variations, committed, actual and cost to complete, by cost code. The project manager closes the month, and the director sees what moved and why.
- Committed cost from approved orders and variations, by cost code
- Cost to complete entered by the person who knows, with the reason kept
- Month-end close with movement against last month
- Every project's contract value, margin and cash on one Work in Hand screen
From awarded quote to paid claim, with the retention accounted for
The subcontract comes from the quote you awarded. Claims are assessed line by line against its schedule, retention is held and released on the dates the contract sets, and the payment schedule goes out on time.
Subcontract
Schedule of items, by location where you want it, retention terms, approval and signing online.
Claim and assessment
The subcontractor claims in their portal; you assess each line, and the difference is explained in the schedule.
Payment schedule
Due dates worked out from the claim and your contract periods, so nothing goes out late.
Retention register
What you hold from subcontractors and what the client holds from you, with every release coming due.
Variations stay joined up: a subcontract variation is linked to the client variation that pays for it, so you see the margin on every change.
| Item | Location | Claimed to date | Assessed to date | This claim | Reason |
|---|---|---|---|---|---|
| Wall linings | Levels 1 to 4 | 412,800 · 100% | 412,800 · 100% | 41,280 | Agreed |
| Wall linings | Levels 5 to 8 | 238,920 · 60% | 179,190 · 45% | 59,730 | Level 8 not started |
| Suspended ceilings | Whole project | 57,300 · 20% | 57,300 · 20% | 57,300 | Agreed |
| Level | Frame | Hydraulic | Electrical | Fire | Board | Paint |
|---|---|---|---|---|---|---|
| Level 8 | ||||||
| Level 7 | ||||||
| Level 6 | ||||||
| Level 5 | ||||||
| Level 4 |
Set up the buildings, levels and units once. Every record finds its place.
Defects, inspections, the site diary, RFIs, drawings and safety are recorded against a building, level or unit, and reported the same way. Ask "what is left on level 5?" and get one answer.
- Inspection and test plans with hold and witness points, by level and unit
- A grid of trade by level that shows who has passed where
- Defects per unit, and a signed handover when the list is closed
- Incidents and observations recorded, actioned and closed
The registers that settle an argument two months later
| Number | Title | Revision | Issued | Linked | Status |
|---|---|---|---|---|---|
| A-2106 | Level 6 floor plan | D | 28 Oct | RFI-041, SUB-018 | Current |
| A-2106 | Level 6 floor plan | C | 2 Sep | RFI-033 | Superseded |
| A-3201 | Section A–A | B | 14 Oct | None | Current |
| A-5410 | Bathroom details, type 2B | A | 3 Nov | SUB-022 | Current |
Drawings
Revisions that supersede the old one, a warning on anything superseded, and the current set to download.
RFIs
Questions to the design team with a due date, a location and the answer kept with the drawing.
Submittals
Shop drawings and samples out for review, back as "revise and resubmit", approved at the next revision.
Correspondence
Letters, notices and instructions in and out, with response dates and the reply on the same thread.
Meetings
Numbered items, actions carried to the next meeting, and minutes issued as a PDF.
Site diary and daywork
Who was on site and what held things up, and signed daywork sheets that become priced variations.
The right person signs off, at the right value, every time
Set who approves each kind of document, in what order and up to what value. Orders, subcontracts, variations, invoices, claims and payments all go through the same workflows, with reminders when a decision is overdue and leave cover when someone is away.
Built for the whole team, from the director to the subcontractor
Directors
Every project's margin and cash on one screen, and the reports to take to the bank.
Commercial managers and QSs
Subcontracts, claims, variations and the forecast, joined up and auditable.
Project managers
Programme, RFIs, submittals and the month-end close, without chasing spreadsheets.
Site managers and foremen
Diary, inspections, defects, safety and daywork filled in on a phone at the work face.
Contract administrators
Correspondence, notices, extensions of time and the paper trail kept in order.
Subcontractors
A portal to quote, sign, claim and keep their insurances current.
Everything SmarteBuild already does, with the commercial layer around it
Take-off from PDF drawings and IFC models, a bill of quantities priced with your own rates, tenders and quote comparison, purchase orders, the client portal and AI that does the typing. They come with Commercial.




Brisbane
Built and supported from East Brisbane. A real phone number, answered weekdays.
Hosted in Australia
Your files and project data sit on Australian servers.
Australian contracts
Progress claims, payment schedules and retention the way they work here.
ABN 29 630 324 006
BREINZ PTY LTD, trading as SmarteBuild.
See it on a project like yours
An hour with the people who build it. Bring a current job; we will walk it from subcontract to claim. Then try it yourself for 30 days, on a project of your own.
